Re: Work at radial - Request for access and update
Date: Wed, 13 Nov 2024 10:07:04 +0530
From: ATDC Auroville Town Development Council <avenir@auroville.org.in>
To: Avinash Ravi Raghavan <aviragh@auroville.org.in>
CC:
vibrance@googlegroups.com, ATDC “L'avenir d'Auroville” Auroville Town
Development Council <avenir@auroville.org.in>
Dear Anandamayi, Chali, Dominique, Lisbeth, Marc, Marco, Matilde, Maya, Peter, Helene,
Marie, Mukta Naradi, Siegrun,Walter, Avinash, Carla, Karan, Rajesh,
We have taken note of your concerns regarding the ongoing radial road work and its impact on
the Madhuca, Sanjana, Arati, and Vibrance communities. We understand your concerns about
the timing of the work, accessibility, and the overall impact on the community.
To address these concerns and find a solution, we have arranged a meeting with you. Jaya and
Prasad have volunteered to meet you at the site to discuss the way forward. We have also
invited Vignesh from CPWD and Candasamy from AVF to join the meeting to expedite the
process of finding an actionable solution.
Please let us know your earliest availability for this meeting so we can finalize a time and date
that works for everyone.
We value your input and are committed to finding a solution that addresses your concerns and
minimizes disruption to the community.
Thank you for your understanding and cooperation.
Warm regards,
L'avenir d'Auroville team
Appointed members: Govind, Hemant (inactive), Jaya, Ponnusamy, Prasad, Sindhuja & Toby
Member-Secretary: Dr. G. Seetharaman
Town Hall, Auroville, Tamil Nadu, India 605101
Page 2 of 2
+91 413 262 2170
avenir@auroville.org.in
'Auroville wants to be a universal town where men and women of all countries are able to live in
peace and progressive harmony above all creeds, all politics and all nationalities.
The purpose of Auroville is to realize Human Unity.'
The Mother
On Sun, 27 Oct 2024 at 18:51, Avinash Ravi Raghavan <aviragh@auroville.org.in> wrote:
Dear Sindhuja/ Govind/ all,
We are disappointed that the work on the radial is happening without any prior communication
to the communities impacted. And that our needs during this considerable work at the only road
accessing our communities are being ignored.
We have learned that this work is estimated to last 3 months and we are concerned that this
work is starting at the very beginning of the monsoon period. At the moment, there is no stable
surface creating a precarious situation for our vehicles and emergency services to pass
through or even access.
The coming rains will only make this worse. Recognizing that we have many elders for whom
navigation on rough, unstable, or slippery surfaces is a challenge, we request that safe access
be given to all communities during the interim and that the removal of the older surface and
application of the new or temporary surface be done in phases so as to minimise disruption.
The Vikas Radial serves its residents well. If one of the main reasons is to create infrastructure
connectivity between the 2 sides of the road every 25m, we request you to reconsider the need
for the huge scale of this current work plan. The spacing between buildings is far more than
25m. We have seen how the Road Service created the sewer line from Vibrance to the
opposite side of the road with minimal disruption and cost. This model could work very well for
the existing radial, while any new parts can use the new design.
We request someone from your team to meet with the impacted communities and provide an
actual update on the plan, timeframe etc. and get input before any more work is done. It can
happen Monday or Tuesday before Diwali, avoiding further disruption while minimising delay.
Thank you,
Avinash (aviragh@auroville.org.in), Carla (95669 36746), Karan, Rajesh