Since I was at the site meeting (Tuesday, 19th Nov) about the Vikas Radial and took part in the
discussion and my name is mentioned in the email below, here are the techinical .points that I
raised then about the roads.
____________________________________________________________________
QUESTIONS FOR AVFO REGARDING THE DESTRUCTION AND PLANNED
RECONSTRUCTION ALONG THE EXISTING VIKAS RADIAL
and
GENERAL ROAD AND PEDESTRIAN INFRASTRUCTURE CONCERNS
____________________________________________________________________
Dear Auroville Foundation Office (Candassamy) and GB (appointed) TDC /
Communications Team (Jaya & Prasad),
Below are points that were brought to the notice of Govind, Jaya and Prasad, GB (appointed)
TDC personnel, and Mr. Candassamy, Auroville Foundation at a meeting on site. We would like
to have your responses on these following points –
● Communication and a community meeting – it was stressed by the community
members residing along the radial that there has to be communication with the
communities of any work that is being executed that affects them. It was agreed that
the GB (appointed) TDC communications team would share the details of the
proposed work that is being carried out and why it is needed.
● They along with Govind also assured that while this road is being dug up alternative
access will be provided for the residents and other users who use this road for all
– the cyclists and motorized vehicles, including emergency vehicles.
● There was a request from the community to share the Work Order from a competent
authority explaining what work is being carried out and the purpose. It should have a
start date and an expected end date, specifications of the work being carried out, and
who is the contractor and site supervisor for this work with their contact information.
● An information board would be erected on the site where the work is being carried
out. It should have the summary of the same information as in the work order, along
with the cost of the work being executed, and the source of funding.
● Technical questions –
Page 3 of 4
Prashant Hedao, PhD
Landscape Architect | Regional Planner | Geographer
Certitude, AUROVILLE
Tel: +91-9443409201
________________________
Consultant, WHO (HQ) GIS Centre for Health
Visiting Faculty, Department of Human Ecology | Landscape Architecture, University of
California at Davis
-------------------
From: Avinash Ravi Raghavan <aviragh@auroville.org.in>
Date: Fri, 22 Nov 2024 at 14:14
Subject: Re: [avenir forwarding] Re: Work at radial - Request for access and update
To: Communication Avenir . <communication-avenir@auroville.org.in>
Cc: ATDC Auroville Town Development Council <avenir@auroville.org.in>, Candassamy N
<candassamy_avf@auroville.org.in>, <Vignesh.mani@gov.in>, Rajesh Shah
<shahrv@gmail.com>, Eric Vibrance <eric.courage@gmail.com>
Dear Jaya, Prasad, Candasammy Sir and Er Vignesh,
Thank you very much for meeting the different community members on Tuesday to set a way
forward. We thought it best to share our notes from this meeting so that we can all be clear and
on the same page. Please do go through and let us know if there are any differences in our
understanding.
Those present -
Jaya, Prasad, Govind (For TDC), Candasammy Sir (Senior Engineer - Auroville Foundation),
Vignesh (Engineer - CPWD), Ganesh (Contractor)
Avinash, Carla, Eric, Ladina, Rajesh (Vibrance), Lisbeth (Madhuca), Naradi (Arati), Isha
(Swayam), Arun (Revelation), Prashant, Rosa and Akira
Outcomes -
● A list of concerns by the communities will be shared and the Avenir communications
team will address these.
● TDC is ready to work with a small team of the residents and will answer community
questions through them. The residents have nominated Avinash, Eric and Rajesh to
represent them.
● The TDC communication team (Jaya and Prasad) acknowledged the lapses in informing
residents about the implementation and the difficulties this caused to the impacted
communities and committed to avoiding this going forward. The TDC communication
team will ensure proper communication to the involved communities about all present
and future work related matters.