From: Prashant Hedao <prashant@auroville.org.in>
Date: Mon, Nov 25, 2024 at 11:32 PM
Subject: Re: [avenir forwarding] Re: Work at radial - Request for access and update
To: Communication Avenir . <communication-avenir@auroville.org.in>
Cc: ATDC Auroville Town Development Council <avenir@auroville.org.in>, Candassamy N
<candassamy_avf@auroville.org.in>, <Vignesh.mani@gov.in>, Rajesh Shah
<shahrv@gmail.com>, Eric Vibrance <eric.courage@gmail.com>, Avinash Ravi Raghavan
<aviragh@auroville.org.in>
Since I was at the site meeting (Tuesday, 19th Nov) about the Vikas Radial and took part in the
discussion and my name is mentioned in the email below, here are the techinical .points that I
raised then about the roads.
____________________________________________________________________
QUESTIONS FOR AVFO REGARDING THE DESTRUCTION AND PLANNED
RECONSTRUCTION ALONG THE EXISTING VIKAS RADIAL
and
GENERAL ROAD AND PEDESTRIAN INFRASTRUCTURE CONCERNS
____________________________________________________________________
Dear Auroville Foundation Office (Candassamy) and GB (appointed) TDC /
Communications Team (Jaya & Prasad),
Below are points that were brought to the notice of Govind, Jaya and Prasad, GB (appointed)
TDC personnel, and Mr. Candassamy, Auroville Foundation at a meeting on site. We would like
to have your responses on these following points –
● Communication and a community meeting – it was stressed by the community
members residing along the radial that there has to be communication with the
communities of any work that is being executed that affects them. It was agreed that
the GB (appointed) TDC communications team would share the details of the
proposed work that is being carried out and why it is needed.
● They along with Govind also assured that while this road is being dug up alternative
access will be provided for the residents and other users who use this road for all
– the cyclists and motorized vehicles, including emergency vehicles.
● There was a request from the community to share the Work Order from a competent
authority explaining what work is being carried out and the purpose. It should have a
start date and an expected end date, specifications of the work being carried out, and
who is the contractor and site supervisor for this work with their contact information.
● An information board would be erected on the site where the work is being carried
out. It should have the summary of the same information as in the work order, along
with the cost of the work being executed, and the source of funding.
● Technical questions –